General : PAC To Probe Sabah Pan Borneo Highway Phase 1 Over Five-Year Delay
Only social or community posts, or a single source.
What happened
[UPDATED] PAC to probe discrepancies in Pan Borneo Highway Sabah Phase 1 project (Google News · The Star, NST, The Edge (no own RSS), 15:00)
The reporting
35 reports- Bernama·News·EN·18 Oct, 18:22 MYT
General : 11.4 Per Cent Figure Does Not Reflect Actual Progress Of Sabah Pan Borneo Highway - Dr Joachim
KUDAT, Oct 18 (Bernama) -- The 11.4 per cent completion rate for the Sabah Pan Borneo Highway project highlighted in the recent Auditor-General's Report does not reflect the actual physical progress on the ground, says Deputy Chief Minister Datuk Seri Dr Joachim Gunsalam.
Read at Bernama - Bernama·News·EN·19 Oct, 12:34 MYT
General : No Payment Delays Affecting Pan Borneo Highway Project - Ahmad Maslan
KUALA LUMPUR, Oct 19 (Bernama) -- There have been no delays in payments to contractors working on the Pan Borneo Highway project that could affect construction progress, Deputy Works Minister Datuk Seri Dr Ahmad Maslan told the Dewan Rakyat today.
Read at Bernama - Bernama·News·EN·19 Oct, 14:21 MYT
General : PAC To Probe Sabah Pan Borneo Highway Phase 1 Over Five-Year Delay
KUALA LUMPUR, Oct 19 (Bernama) -- The Public Accounts Committee (PAC) has launched an investigation into the management, financial governance and physical implementation of Phase 1 of the Sabah Pan Borneo Highway project following revelations in the Auditor-General’s Report…
Read at Bernama - nst.com.my·News·EN·17 Oct, 15:00 MYT
[UPDATED] PAC to probe discrepancies in Pan Borneo Highway Sabah Phase 1 project
Read at nst.com.my - nst.com.my·News·EN·18 Oct, 18:01 MYT
11.4pct figure does not reflect actual progress of Sabah Pan Borneo Highway - Dr Joachim
Read at nst.com.my 
Photo: Free Malaysia Today Free Malaysia Today·News·EN·18 Oct, 18:06 MYTSabah Pan Borneo Highway progress higher than 11.4% in A-G report, says DCM
Sabah deputy chief minister Dr Joachim Gunsalam said the 11.4% figure only measured the number of fully handed-over packages, which accounted for just four of the 35 packages under Phase 1 of the project. (Bernama pic) KUDAT: The 11.4% completion rate for the Sabah Pan Borneo…
Read at Free Malaysia Today- malaysiakini.com·News·EN·18 Oct, 18:23 MYT
Sabah Pan Borneo project: Figures cited by AG report doesn't reflect actual progress - Sabah DCM
Read at malaysiakini.com /file/publisher-c1a3f893382d2b2f8a9aa22a654d9c97/2025/07/d56934a6be8486ecf8b3b4a0f3533d29.jpg)
Photo: Malaysiakini (EN) Malaysiakini (EN)·News·EN·18 Oct, 18:23 MYTSabah Pan Borneo project: Figures cited by AG report doesn't reflect actual progress - Sabah DCM
Some alignments recording between 90 and 93pct physical progress, Joachim says.
Read at Malaysiakini (EN)- Sarawak Tribune·News·EN·18 Oct, 18:28 MYT
Dr Joachim: 11.4% completion rate doesn’t reflect true progress of Sabah Pan Borneo Highway
KUDAT, Sabah : The 11.4 per cent completion rate for the Sabah Pan Borneo Highway project highlighted in the recent Auditor-General’s Report does not reflect the actual physical progress on the ground, says Deputy Chief Minister, Datuk Seri Dr Joachim Gunsalam. The Sabah Public…
Read at Sarawak Tribune 
Photo: Berita Harian Berita Harian·News·BM·19 Oct, 12:10 MYTIsu bayaran bukan punca Lebuh Raya Pan Borneo lewat - Ahmad Maslan
KUALA LUMPUR: Kementerian Kerja Raya (KKR) menafikan dakwaan pembayaran lewat sebagai punca Lebuh Raya Pan Borneo gagal dibina mengikut jadual asal pelaksanaan projek. Timbalan Menterinya, Datuk Seri Dr Ahmad Maslan, berkata ia sebaliknya berpunca akibat masalah dalam kalangan…
Read at Berita Harian
Photo: Utusan Malaysia Utusan Malaysia·News·BM·19 Oct, 12:30 MYTMasalah kontraktor antara punca kelewatan Lebuhraya Pan Borneo
PETALING JAYA: Penamatan perjanjian Rakan Pelaksana Projek (PDP) pada 2019 dan masalah kontraktor antara punca Lebuhraya Pan Borneo (LPB) gagal dibina mengikut jadual asal pelaksanaan projek. Timbalan Menteri Kerja Raya, Datuk Seri Dr.
Read at Utusan Malaysia
Photo: Free Malaysia Today Free Malaysia Today·News·BM·19 Oct, 12:45 MYTPAC siasat pengurusan, pelaksanaan Pan Borneo Sabah Fasa 1
PAC berkata projek Lebuhraya Pan Borneo Sabah Fasa 1 sepatutnya siap sepenuhnya pada hujung 2021, namun sebahagian besar pakej masih dalam pelaksanaan. (Gambar Bernama) PETALING JAYA: Jawatankuasa Kira-Kira Wang Negara (PAC) akan memulakan siasatan terhadap pengurusan, tadbir…
Read at Free Malaysia Today- utusan.com.my·News·BM·19 Oct, 12:58 MYT
Lebuhraya Pan Borneo: PAC mulakan siasatan menyeluruh
Read at utusan.com.my 
Photo: Utusan Malaysia Utusan Malaysia·News·BM·19 Oct, 12:58 MYTLebuhraya Pan Borneo: PAC mulakan siasatan menyeluruh
PETALING JAYA: Jawatankuasa Kira-Kira Wang Negara (PAC) akan memulakan siasatan menyeluruh berhubung pengurusan, tatakelola kewangan serta pelaksanaan fizikal Projek Lebuhraya Pan Borneo (LPB) Sabah Fasa 1. Pengerusi PAC, Datuk Mas Ermieyati Samsudin berkata, pihaknya memandang…
Read at Utusan Malaysia
Photo: KiniTV (YouTube) KiniTV (YouTube)·YouTube·BM·19 Oct, 13:36 MYTLebuhraya Pan Borneo lewat 5 tahun, RM10.547 bilion dibelanjakan! - PAC mulakan siasatan
Jawatankuasa Kira-Kira Wang Negara (PAC) akan memulakan siasatan menyeluruh berhubung pengurusan, tatakelola kewangan serta pelaksanaan fizikal Projek Lebuhraya Pan Borneo (LPB) Sabah Fasa 1. Pengerusi PAC Mas Ermieyati Samsudin berkata, pihaknya memandang serius dapatan…
Read at KiniTV (YouTube)- hmetro.com.my·News·BM·19 Oct, 13:46 MYT
PAC siasat kelewatan Projek Lebuhraya Pan Borneo Sabah
Read at hmetro.com.my - theedgemalaysia.com·News·EN·19 Oct, 13:46 MYT
Parliament committee to probe Sabah’s side of Pan Borneo Highway project
Read at theedgemalaysia.com - freemalaysiatoday.com·News·EN·19 Oct, 13:48 MYT
PAC to probe management of Sabah Pan Borneo Highway project
Read at freemalaysiatoday.com 
Photo: Free Malaysia Today Free Malaysia Today·News·Mixed·19 Oct, 13:48 MYTPAC to probe management of Sabah Pan Borneo Highway project
The A-G's report noted that the Sabah Pan Borneo Highway project remained incomplete as of March 31, 10 years after it was planned, despite the transfer of management from the delivery partner to the works ministry in September 2019. (Bernama pic) PETALING JAYA: The Public…
Read at Free Malaysia Today- bharian.com.my·News·BM·19 Oct, 13:55 MYT
PAC mula siasat Fasa 1 Lebuh Raya Pan Borneo Sabah
Read at bharian.com.my - bharian.com.my·News·BM·19 Oct, 13:56 MYT
PAC siasat projek Pan Borneo Sabah, RM10.5 bilion dibelanja, sepatutnya siap lima tahun lalu
Read at bharian.com.my 
Photo: Free Malaysia Today Free Malaysia Today·News·BM·19 Oct, 13:57 MYTTiada kelewatan bayaran dalam projek Lebuhraya Pan Borneo, kata Ahmad Maslan
Timbalan Menteri Kerja Raya, Ahmad Maslan berkata wujud isu melibatkan prestasi kontraktor yang perlu diatasi bagi memastikan projek Lebuhraya Pan Borneo berjalan lancar serta mengikut jadual. (Gambar Bernama) KUALA LUMPUR: Tiada kelewatan pembayaran kepada kontraktor projek…
Read at Free Malaysia Today/file/publisher-c1a3f893382d2b2f8a9aa22a654d9c97/2026/08/cb32a92b149d4d58fe597ae7c53afdc5.jpg)
Photo: Malaysiakini (BM) Malaysiakini (BM)·News·BM·19 Oct, 14:27 MYTPAC siasat kelewatan projek Pan Borneo Sabah
Ini susulan kelewatan serta kelemahan pelaksanaan dan pemantauan yang dibangkitkan dalam Laporan Ketua Audit Negara.
Read at Malaysiakini (BM)- malaysiakini.com·News·EN·19 Oct, 14:38 MYT
PAC to probe Sabah Pan Borneo Highway project following AG report's findings
Read at malaysiakini.com /file/publisher-c1a3f893382d2b2f8a9aa22a654d9c97/2026/02/6ca4b719b2545f139d3f4235187360e1.jpg)
Photo: Malaysiakini (EN) Malaysiakini (EN)·News·Mixed·19 Oct, 14:38 MYTPAC to probe Sabah Pan Borneo Highway project following AG report's findings
We will examine how delays occurred despite existence of oversight committees - Mas Ermieyati.
Read at Malaysiakini (EN)- astroawani.com·News·BM·19 Oct, 15:00 MYT
Lewat lima tahun, PAC siasat pelaksanaan Pan Borneo Sabah Fasa 1
Read at astroawani.com 
Photo: Astro Awani (BM) Astro Awani (BM)·News·BM·19 Oct, 15:00 MYTLewat lima tahun, PAC siasat pelaksanaan Pan Borneo Sabah Fasa 1
awatankuasa Kira-kira Wang Negara (PAC) Parlimen memulakan siasatan berhubung pengurusan, tatakelola kewangan dan pelaksanaan fizikal Projek Lebuhraya Pan Borneo (LPB) Sabah Fasa 1.
Read at Astro Awani (BM)- umno-online.my·News·BM·19 Oct, 15:08 MYT
Pan Borneo Sabah: Pelaksanaan Projek Hampir Siap – Ahmad Maslan
Read at umno-online.my 
Photo: Malay Mail Malay Mail·News·EN·19 Oct, 15:23 MYTPAC launches probe into Sabah Pan Borneo Highway after audit reveals delays despite RM10.5b spent
KUALA LUMPUR, Oct 19 — The Public Accounts Committee (PAC) has launched an investigation into the management, financial governance and physical implementation of Phase 1 of the Sabah Pan Borneo Highway project following revelations in the Auditor-General’s Report (LKAN) Series…
Read at Malay Mail
Photo: The Star (YouTube) The Star (YouTube)·YouTube·Mixed·19 Oct, 16:07 MYTPAC to probe Sabah Pan Borneo Highway project, says Mas Ermieyati
The Public Accounts Committee (PAC) will investigate the management, financial governance and physical implementation of the Sabah Pan Borneo Highway Phase 1 project. PAC chairman Datuk Mas Ermieyati Samsudin said the decision followed concerns raised in the Auditor-General’s…
Read at The Star (YouTube)- berita.rtm.gov.my·News·BM·19 Oct, 16:12 MYT
Isu pembayaran bukan punca kelewatan pembinaan LPB Sabah
Read at berita.rtm.gov.my 
Photo: The Star (YouTube) The Star (YouTube)·YouTube·EN·19 Oct, 16:14 MYTNo payment delays affecting Pan Borneo Sabah project, Parliament told
There have been no delays in payments to contractors working on the Pan Borneo Highway project in Sabah that could affect construction progress, says Deputy Works Minister Datuk Seri Dr Ahmad Maslan. He said payments for Phase 1A and Phase 1B were made based on work completed,…
Read at The Star (YouTube)
Photo: Kosmo! Kosmo!·News·BM·19 Oct, 16:23 MYTPan Borneo Sabah siap sepenuhnya 2030
KUALA LUMPUR – Projek Lebuhraya Pan Borneo (LPB) Sabah sepanjang 706 kilometer dijangka siap sepenuhnya pada 2030, dengan kemajuan fizikal Fasa 1B ketika ini baru mencapai 23.96 peratus. Timbalan Menteri Kerja Raya, Datuk Seri Ahmad Maslan berkata, daripada keseluruhan 35 pakej…
Read at Kosmo!
Photo: KiniTV (YouTube) KiniTV (YouTube)·YouTube·Mixed·19 Oct, 18:31 MYTPAC to probe Sabah Pan Borneo Highway project
The Public Accounts Committee (PAC) will launch an investigation into the Sabah Pan Borneo Highway project following delays and weaknesses found in its implementation and monitoring. This comes after the 2026 Series 2 Auditor-General’s Report (AG report) highlighted a series of…
Read at KiniTV (YouTube)- The Vibes·News·EN·19 Oct, 15:11 MYT
PAC to probe Sabah Pan Borneo Highway delays despite RM10.5b spent
THE Public Accounts Committee (PAC) will investigate how RM10.547 billion was spent on the Sabah Pan Borneo Highway Phase 1 project, with only four of its 35 work packages completed despite the project being scheduled for completion in 2021. PAC chai...
Read at The Vibes
Headlines, short summaries and photos belong to the outlets credited; each report is read on the outlet's own site.
Why it is over
- No engagement data available from these sources; score uses mention signals only
- Discussed in English, mixed-language
Attention graph
Not enough history in this window yet. The engine measures every five minutes.
Timeline
- DetectedFirst detected (Google News · The Star, NST, The Edge (no own RSS)) source
- NewsFirst news outlet reports it (Google News · The Star, NST, The Edge (no own RSS)) source
- LanguageFirst mixed-language coverage (Free Malaysia Today) source
- StateOver
single source and no mention for 47h
- SpreadYouTube discussion begins (The Star (YouTube)) source
- StateOver
single source and no mention for 42h
Where it started
How it spread
- Step 1News outletsGoogle News · The Star, NST, The Edge (no own RSS)15:00
- Step 2NewsThe Vibes15:11 · +2891 min
- Step 3YouTube (mainstream)The Star (YouTube)16:07 · +2947 min
Internet reaction
- Sabah Pan Borneo Highway – actual progress of project is higher than reported 11.4% completion: Deputy CMu/Mick Chan · Paul Tan's Automotive News · 10:33 · EN
- PAC to probe Sabah Pan Borneo Highway delays despite RM10.5b spentu/The Vibes · The Vibes · 15:11 · EN
- PAC probing delay in Sabah Pan-Borneo Highway project despite billions spentu/Scoop Reporters · Scoop · 15:38 · Mixed
What we know
- Reported by an official source (Bernama)
- Covered by 10 established outlet(s): Bernama, Free Malaysia Today, Free Malaysia Today (YouTube), Google News Malaysia (ZH)
What we don’t know
- Independent confirmation is missing; treat specifics as unverified
All sources (47)